|
CRI Project
Update/BSB Occupant's Meeting
January 10 BSB 120
- Jack Buchanan and the
Physical plant have restored the gas distribution system to the East
(dental) end of the Building. They are hopeful that they will be successful
in restoring the West end in the very near future, although many leaks
and many feet of piping remain to be tested and repaired. In a meeting
earlier today, Dr. Hook expressed his appreciation to both Jack and
the Physical Plant for their diligence in pursuing the malfunction
and repair of the gas system and for their excellent communication
throughout the ordeal.
- Hal Currey noted that
MUSC Risk Management deserved recognition for their responsiveness
and professionalism during this gas system crisis, as well.
CRI Update
- Mac McClinton reported
that:
- the Piling Load Test
results indicate that the structural pilings may be reduced in length
by as much as 10 feet per pile.
- although weather delayed
some of their work last week, they were able to complete a section
of the duct bank for the underground electrical distribution system.
- work on the temporary
loading dock will begin shortly.
- they switched from the
"B" to the "A" electrical power feed and that the building is running
well on the A feed. The B feed will remain in place for a few days
to be certain that the A feed can carry the load adequately.
- Pharmacology's Mass
Spectrometer was delivered last week. John Brubaker expressed his
appreciation to Hank and Mac for their help in getting the equipment
off loaded and delivered safely.
Infrastructure
Update
- the change order for sound
attenuation on the exhaust fan on the west end of the building has
been approved and work will begin soon.
- bond money has been approved
for phase II, which includes the mechanical room expansion.
Dr. Swindle (DLAR) asked
about the status of his autoclave and food locker since they are located
adjacent to the existing loading dock that will soon be inaccessible.
Mac McClinton assured Dr. Swindle that the autoclave and the food locker
will remain accessible throughout the duration of the project. Dr. Swindle
reminded the group that AAALAC inspection is very soon-Feb 8, 2002.
Dr. Schwartz asked if the
filters had been installed on the auxiliary air intakes that feed the
inner labs of the second floor. Mac responded that these filters had
been requested through the project some weeks ago and he thought they
had been installed. Dr. Schwartz said he could smell diesel fumes during
the excavation the previous day and asked if something more could be
done. Note: It was determined that, in fact, the filters had never been
ordered so Mac ordered the filters through MB Kahn and asks that they
be installed as soon as they arrive.
Next week's activities:
(Jan 14-18)
- move the telephone cable
that is running through the construction site.
- accept delivery of the
temporary fuel tank and remove the existing unit.
- install additional duct
bank footage.
- begin the temporary loading
dock.
Attendees: Jack Buchanan
Hal Currey Hank Harrison Leslie Kendall John Malmrose Mac McClinton
Boyd Wood Mike Swindle Scott Reid Jerry Ondo David Schwartz Cliff Harvey
Beth Gladden John Brubaker
|