Although
numerous diagnostic tests have been performed and repairs made,
the gas distribution system is still down. At least for now, all
departments in BSB will have to consider an alternate source for
their gas needs. Alcohol burners are available from the P-plant
but propane torches have not yet arrived; they are due Monday.
-
The Piling
Load Test results are in: positive results indicate a possible reduction
of piling length-perhaps as much as 10 feet.
-
Weather
delays have postponed much of the excavation work planned for this
past week, but will continue next week.
-
Pharmacology's
Mass Spec will be arriving Monday so access to loading dock will
be necessary.
-
The compactor
near the loading dock needs to be moved offsite but can be re-placed
in a few days.
There is an asbestos pipe beneath the "B" electrical feed and within
the footprint of the new building that must be removed.
-
A very
brief electrical outage is required in order to transfer from power
feed B to A. This outage will be Thursday, Jan 10 at 0600. It will
not affect emergency power. Outage notification is required.
-
Attendees:
Jack Buchanan Hal Currey Hank Harrison Leslie Kendall John Malmrose
Mac McClinton Dean Mills Peggy Schachte Rick Terhune Boyd Wood