|
CRI Project Update/BSB Occupant’s Meeting
January 31 BSB 120
Next meeting: February
7, 1:30 p.m., BSB120
Infrastructure progress
- Westend exhaust system--
Mac McClinton reviewed the infrastructure progress. The sound attenuation
on the westend exhaust system is complete.
- East air handler--
In the near future, the east air handler will have to be shut down
for a short period of time so that a brace can be installed. The brace
is needed to support the roof, which is bowing slightly, and to keep
further deterioration from occurring.
- Air intake filters--
Dave Dement changed the air intake filters on Tuesday. He will be
checking interior filters weekly and changing as often as needed.
He will be replacing the media on the outside prefilters every week.
Dave will be in touch with Dr. Schwartz to see if these filters have
eliminated the problems. Dr. Schwartz still smells diesel fumes from
time to time in his lab.
- Replacement fuel tank--
The utilities are being marked today that go to the west end replacement
fuel tank. The DHEC permit process has started. This is a 20,000-gallon
tank, which replaces the one in the back, and another will be added
in the future. This is a 90-day duration project, which should be
completed in late April.
Sheet piling is being vibrated down; dewatering will take place so
the slab under the original tank can be removed. The northeast entrance
and sidewalk will be closed for about a week while dewatering takes
place.
- BSB Security--
Concern over the lock down of BSB was discussed. Leslie Kendall agreed
to report the details of the proposed security measures to BSB occupants
as soon as they were available. She reminded the group that no measures
would be implemented without the occupants' input.
- Radioactive waste--
Concern over radioactive waste disposal was expressed. Hank Harrison
will be contacting Radiation Safety this week. A ramp may have to
be build this week to accommodate this disposal. Leslie Kendall will
talk with Jim Rutan (Radiation Safety) and get an email to the occupants
before next Wednesday outlining the procedure.
- B-feed-- We will
replace the old B-feed from the substation to CRI; this is being replaced
because of the age of wire. The A-feed (current active feed) was replaced
in July.
- MRE-- The design
for the new Mechanical Room has started. The actual structure will
be bid on first, then the engineering of the contents of the building
will be bid on in the spring. The building should be up and running
by the following Spring, 2003.
- BSB Lobby-During
the building of CRI, the lobby of BSB will be completely refurbished--
both the elevator lobby and the lobby currently occupied by Food Services.
The elevators will be completely reworked and the monumental stairs
to the second floor will be added. Greg Soyka, the architect for this
project, will come to our meeting Feb 14 to show us the drawings and
finishes for this renovation. The work is not likely to begin before
Summer 2002 and will be done in stages to minimize the inconvenience
to the BSB occupants.
- The autoclave--The
autoclave on the loading dock will have to be removed to make room
for the stairs. Before this work can begin asbestos abatement will
have to be done. A tunnel may have to be built to allow for the abatement
in the area. Although this renovation will come at great inconvenience
to the occupants it is part of the overall improvement of the building
and should be completed before Dr. Ondo retires… maybe.
- Attendees: Mac
McClinton Hank Harrison Jack Buchanan Scott Reid Beth Gladden Dr.
Bill Ledbetter Bud Cooper Cliff Harvey John Brubaker Dr. David Schwartz
Dr. Jerry Ovdo Dr. Ed Krug Dr Thomas Trusk
|