CRI Project
Update/BSB Occupant's Meeting
February 20, 2003 BSB 120
Next meeting: March 6, 2002, 1:30 p.m., BSB120
Lockers
– Marisa McEntire, IDC Design Project Manager, gave
an update on the Proteomics Research Center renovation project. Room
103 (currently the men’s locker room) will be renovated into
a proteomics lab space. Asbestos abatement will be performed as well.
158 lockers will be moved from 103 to room 115. The mailboxes in room
115 will be removed and the floor tile and paint redone.
The adjoining men’s restroom (103A) will remain a restroom with
showers and a few lockers, but will have the entrance moved to the
hallway rather than from room 103. Card key access and a panic button
will be added to the restroom.
The women’s locker room/restroom (113) will also be renovated
during this project, as previously reported. Cardkey access and a
panic button will be added to the ladies’ locker room. However,
plans are not fully finalized for this renovation as yet.
Air
Handler #5- The replacement for air handler 5, that serves
Cell Biology and Anatomy is on site and will be installed early in
March.
MRE and CRI—These two projects have been officially
combined into one.
The requirement of conditioned air for the finishes in the CRI caused
a 30-day impact on the overall schedule. Thankfully we were 30 days
ahead of schedule so the May 04 completion date is still attainable.
There are 12 pending weather days in the current change order request,
which, if granted, will provide some additional cushion.
The pile caps and tunnel are placed; slab for the tunnel is in progress.
Sumter Utilities work, which is the high voltage feeder project, is
almost complete with respect to the CRI site. The site's space problems
will ease when Sumter moves their equipment.
The permit is approved and in hand for the underground storage tank.
The underground chilled water piping is complete. The storm sewer,
which has been problematic because of underground obstructions, can
start next week.
CRI- The structural steel frame now continues up
to the 7th floor; concrete is up to the 4th floor. The basic steel
for the building should be finished by mid March. Concrete block and
exhaust ductwork will begin March. The planned water outages last
weekend allowed the vac, air and gas piping to be completed.
Lobbies
– The delivery of the 2nd floor stairwell steel has
been delayed by 21 days, which has negatively impacted the schedule
for reopening the lobbies. Setting of the staircase steel will begin
in early March.
On the 2nd floor, half of the metal floor to ceiling framing has been
installed; lights are roughed in.
Apr 18th was the opening date for the 2nd floor lobby; June 17th was
the completion date for both lobbies. At the next occupants’
meeting we will present an updated flow schedule showing precisely
the impact the delay has caused. The overall contract finish date
for the building has not changed—Apr 04.
Covering
windows – A number of windows will be covered where
the new CRI meets BSB. It was specified by the contractor that sheetrock
would be placed over the inside of the windows so that the result
would be a flush, continuous wall. Some occupants have objected to
the intrusion that would be caused by the contractor performing structural
and sheetrock work in the labs. They have asked if the windows could
simply be painted black from the outside and mini blinds installed
over them. It was suggested that the sheetrock work could be performed
at a later date when lab renovations or reassignment occur. Here are
the room numbers where windows will be covered. If you have a preference
for one of the two procedures described above, please let me know.
2nd floor-
226, 225, 224, 227, (6 windows in 230)
3rd floor- 332, 332a, 332b, 332c, 335a 327, 327a, 326
4th floor- 431, 422, 420
5th floor- 530, 531, 535b, 535c, reception area 535
6th floor- 633, 635, 635a, 630, 629, 627, 626
7th floor- 729,731,734, 734a, 724-726
Diesel
Fumes -- Occupants continue to suffer the nuisance of diesel
fumes. It has not yet been determined whether the louvered vents above
the windows are open or closed.
Issue
update: Inspection of windows on the south side of the second
floor revealed that all louvered openings were sealed. Eight outside
air intakes on 2nd floor west end appeared to be in good condition;
the dampers were closed, but plans are to seal these from the outside
as an additional precaution. A cover on the large opening behind the
switch gear on the 1st floor had been removed; it will be reinstalled
Feb 28, 03. No open louvers were found above the south side 3rd floor
windows. Suites BS 335 and 238 were not accessible at the time of
inspection but will be inspected as soon as possible.
Carbon filters
that were changed Feb 11 have been tested and were saturated.
Occupants
would like to have a representative from OSH attend the next meeting
(March 6, 1:30) so that questions can be addressed directly to them
concerning the latest BSB air quality monitoring report. The report
is below:
Re:
Nitrogen Dioxide, Sulfur Dioxide, Carbon Monoxide
And Diesel Exhaust Particulate Sampling, Basic Science Building
Dear
Mr. Avant,
On
February 18, 2003 area samples for the above referenced air contaminants
were collected in room 128 and the oral surgery office on the second
floor. Samples were collected in the morning and afternoon for NO2,
SO2, and CO. using detector tubes. Samples for
Diesel Exhaust Particulate were collected continuously for approximately
4 hours using battery-operated pumps placed near workstations in the
offices.
Results
show no detectable levels of for NO2, SO2,
or CO. The detection limit is well below the OSHA Permissible Exposure
Limits and the ACGIH Threshold Limit Values. Results of the testing
for Diesel Exhaust Particulate show no detectable levels in room 128
and 4.8 ug/m3 for elemental carbon. OSHA currently does not have a
standard for Diesel Exhaust. The Conference of American Industrial
Hygienists has a proposed standard of 20 ug/m3. The results are well
below this proposed standard. The final report will follow in a few
days. If I can answer any questions, please feel free to contact me.
Sincerely,
TRIDENT ENVIRONMENTAL SERVICES, INC.
C. Michael Underhill, CIH, CSP
President
Construction
project noise—
"Valerie
T. West, Ed.D." wrote:
In
my recent meeting with SGA reps, the issue of construction noise in
BSB during exams was brought up. I've spoken with Leslie Kendall (e-mail
attached) who is coordinating the construction. She has agreed to
work with us on this when at all possible. Please let her know in
advance of times when your students will be taking exams in BSB and
she will work toward avoiding noisy activity during those times.
I recognize there may be other times that are crucial as well - like
regular classes. I also know we must proceed with the building..if
we work together, perhaps we can make this as painless as possible.
Thanks,
Valerie
Indeed we
will do all we can to accommodate exam schedules; plenty of advance
notice will help. Thanks for your patience thus far... the project
is on schedule at this time. We are hopeful that a contract completion
date of April 04 can be maintained.... April 04…so close, yet
so far away...!
Meeting
Attendees- Mac McClinton, Hal Currey, Dr. Jerry Ondo, David
Schwartz, Dwayne McMillan, Marisa McEntire, Charles Darby, Cliff Harvey,
Bud Cooper, Tom Trusk, Leslie Kendall, Laura Walters
|