|
|
||||||
| CRI
Project Update/BSB Occupants’ Meeting
February 6, 2002 BSB 120 Next meeting: February 20, 2002, 1:30 p.m., BSB120 CRI – Currently the CRI construction project schedule has recovered a month due to the additional crane and steel crew. Most of the vertical columns are complete, horizontal steel beams are in place to the 6th floor, and the steel decking is complete to the 4th floor and has started on the 5th. The suspended slab on floors 1-4 will be completed by the end of the month. Soon, roof slab will be set, which is critical to the setting of the two major air handlers on the roof.
There will be several types of utility outages needed in the next two weeks in order to proceed. Minor local outages of gas and vacuum to hook in the utilities will be necessary, as well as, a building wide outage of domestic hot and cold water, which will be scheduled for sometime during the holiday (Feb 14-17) weekend. This will be about an 8-hour outage. Notification of all scheduled outages will be broadcast to the occupants. Many thanks to the Facilities & Engineering crews for conducting these outages at a time that is less disruptive to the researchers. The first floor main lobby renovation is currently about a week behind schedule. The 2nd floor lobby is scheduled to be reopened by April 1, 2003. The renovation of the elevators will continue with the replacement of all elevator cars, one at a time. The controls to the east elevators have been upgraded. Unfortunately, during this upgrade the button inside the elevator that flashes during a fire alarm was not connected properly, so the elevators failed the inspection. The elevators will be re-inspected when this problem is corrected. The good news is, that it was determined that the audible alarm could be bypassed during testing, so future tests will be transparent to the occupants. MRE – Foundation for the mechanical room expansion should begin by mid March. Setting of steel should begin by May. The completion of this building continues to lag about five months behind schedule. There are alternate sources of chilled water and power to operate the completed CRI if the MRE schedule does not improve-- taking chilled water from the hospital loop and a temporary generator for power.
Malodorous diesel fumes continue to plague the occupants of BSB. In response to your calls to the Facilities & Engineering Help Desk (792-4119) to report the presence of diesel fumes, OSHP has reported the following:
And from Mac
McClinton, when asked how these odors enter the building: When the BSB windows were supplemented with additional exterior units at each existing window location a couple of years ago, some of the louvers above the windows did not get sealed. If the building pressure is allowed to "go negative" to any degree, these openings will pull air in from the exterior. If it is warm moist air, condensation may result if conditions favorable are present. If the air is carrying odors, those will be wafted in continuously. Perhaps we should focus on the condition of every window louver, and monitor the relationship of the supply and exhaust to ensure the best relationship exists between the safety of the occupants using fume hoods, and the environmental concerns of as much positive pressure as possible in the building to discourage air infiltration. (Author’s note: The carbon filters in the air handler were replaced on Feb 11th. Covering the window louvers is being addressed by Facilities and Engineering.)
|
||||||
|
Content last updated: Friday, 21 February, 2003 |
||||||