|
CRI Project Update/BSB Occupant’s Meeting
February 7, 2002 BSB 120
Next meeting: February
14, 1:30 p.m., BSB120
Infrastructure progress
- The west end air handler
test and balance can begin as soon as the following work is done:
control valve work, asbestos abatement and ductwork.
- The plastic pipes that
were initially installed for the Cooling Tower will be replaced with
black steel pipes because we have suffered about 12 blowouts at the
fittings of the plastic pipes in the past 2 years.
- The proposed Mechanical
Room will house 2 stacks for boilers, all switch gear, chillers and
cooling towers. The building will have to be 2 stories and approximately
80 feet high by 50 feet wide. The plan now is to put this building
on the west end. Mac is concerned with the planned location because
of the size and the noise emanating from this building. Mac asked
Boyd Wood to go back to the Master Plan of the MUSC campus and to
review this location and how this building is going to affect the
MUSC campus. Considering the new research facilities planned along
Bee Street and the new Dental Building in the adjacent area it may
be that a Central Energy Facility is a more viable option. The
design of the structure should be finished in 30 days. This building
needs to be on line in about a year.
CRI Update
- The critical path is still
thru the relocated duct bank, then piles and pile driving. The new
duct bank has been installed from G lot to Waring Library.
- Pile driving will start
next week and will take about 6-8 weeks. Tunnel pile driving will
begin on about March 15th. These will be the closest to the building
and, perhaps, the noisiest.
- The $2,000,000 NIH grant
has been funded for animal facilities upgrades including a transgenics
facility, a tunnel wash and an autoclave.
- Pouring of concrete for
the foundation will start in late February. This is one of the significant
milestones of any construction project. According to the old timers,
once concrete is poured the building seems to go up very quickly.
- Hank Harrison reported
that another sidewalk would be poured by the Waring Library and the
back and east end of the building will get cleaned up. The water will
be pumped out over the weekend and hopefully that area will dry.
- Leslie Kendall reported
progress with the radioactive waste disposal. Occupational Safety
and Health agreed that if she could find some space by or near the
old loading dock where the waste could be collected they would take
the waste from there to the trailer.
- John Brubaker reported
that the waste trailer also serves as a decay facility, so access
is still important. A new ramp is being built to the trailer to facilitate
those needing access.
- Leslie Kendall reported
that little new information was available on security at BSB, but
that a meeting was scheduled for 3:00 p.m. today for an update. It
is important for occupants of BSB to know that no decisions will be
made regarding heightened security measures in their building without
their input.
- At the next meeting of
the CRI/BSB Occupants' group, Greg Soyka will be here to show the
plans and finishes for the lobby renovation.
- Attendees: Cliff
Harvey Mac McClinton Leslie Kendall Hank Harrison Laura Walters Boyd
Wood John Brubaker Scott Reid Beth Gladden
|