CRI Project Update/BSB Occupants' Meeting
April 25, 2002 BSB 120

CRI

In preparation for the eventual breakthrough at every floor of BSB, restroom asbestos abatement and renovation has begun. Through the end of June these activities will be performed per the following schedule:

Asbestos Abatement Renovation
5th floor restroom (SE end), April 30 6th floor restroom, May 6
2nd floor restroom (NE end) May 6 2nd floor restroom, May 13
3rd floor restroom, May 13 7th floor restroom, June 24
4th floor restroom May 20  
5th floor restroom June 3  
2nd floor restroom June 10  
7th floor restroom June 17  

Sheet piling is in progress for the utilities tunnel. Dr. David Schwartz reported that in his lab the occupants have felt vibrations from the work being done. H-pile driving has been completed. Excavating and forming the foundation is proceeding. Concrete is being poured May 1, 2002.

The northwest back door of BSB will be closed to pedestrian traffic for the duration of the construction. The back doors may be used for deliveries and services only.

Adrianne McLain from Occupational Safety and Health reported on the current status of the Infectious Waste Disposal program. It is operating under a temporary contract until a permanent solution is resolved. She would like to help make the program more efficient and needs input from the BSB occupants. Scott Reid suggested that Adrianne attend the lab managers' meeting that is held each month on the 2nd Thursday. Beth Gladden is going to send her a list of all department and lab managers.

Jack Buchanan is initiating a weekly BSB elevator inspection program. Occupants can assist by reporting any problems they encounter with the elevators to 2-4119.

Attendees: Beth Gladden Adrianne McLain Mac McClinton Jack Buchanan Dwayne McMillian Leslie Kendall Laura Walters Hank Harrison Scott Reid David Schwartz Cliff Harvey John Brubaker