CRI Project Update/BSB Occupants' Meeting
May 2, 2002 BSB 120


Restroom asbestos abatement is in progress now on the 5th floor and renovation will begin on May 6th on the 6th floor. Through the end of June these activities will be performed per the following schedule:

Asbestos Abatement Renovation
5th floor restroom (SE end), April 30 6th floor restroom, May 6
2nd floor restroom (NE end) May 6 2nd floor restroom, May 13
3rd floor restroom, May 13 7th floor restroom, June 24
4th floor restroom May 20  
5th floor restroom June 3  
2nd floor restroom June 10  
7th floor restroom June 17  

Utilities tunnel sheet piling is nearing completion and excavation is to start on May 6, 2002.

100 yards of foundation concrete was placed on Wednesday, May 1.

Jack Buchanan is initiating a weekly BSB elevator inspection program. Jack has assigned one person to check elevators weekly. Cliff Harvey reported that the elevators are working much better. Way to go, Jack!!!!!! Occupants can assist by reporting any problems they encounter with the elevators to 2-4119. Structural Steel Review A meeting was conducted on May 1,2002 with the steel fabricator, general contractor, architect, and structural engineers.

MRE A presentation to the Charleston BAR is planned for May 8, 2002 to review the progress drawings of the mechanical room expansion. These drawings were presented at the Occupants' Meeting.

Thefts on Construction site Tools and a calculator were stolen from the construction site last week. The calculator had some valuable information stored in it. Restoring the information to the calculator will be difficult for the Construction Project Manager. The return of the calculator would be greatly appreciated.

PLEASE NOTE THE NEXT MEETING WILL BE HELD IN BSB409

Attendees Mac McClinton Jack Buchanan Joe Pelton Charlie Darby Cliff Harvey John Brubaker Hal Currey Thomas Trusk Dwayne McMillian Hank Harrison