|
|
||||||
| CRI
Project Update/BSB Occupants’ Meeting Next meeting: August 7, 2003, 1:00 p.m., BSB 120 MRE-
The structure steel system is complete and the concrete has been poured
up to the third floor. The roof has been placed. The energy efficient
chiller has been set on the first floor. The equipment listed below
will be delivered in August 2003 and will be set on different floors
of the MRE by September 2003.
The next phase of work includes securing chilled water for the new and existing buildings. This will involve the following:
Next, we will tap into the existing steam loop from the hospital and run about 60’ of pipe into the tunnel. Then all pipe in the existing building and a new steam station will be put into service. Combined, these three phases of work will complete the heating and cooling system for the BSB, CRI and MRE. We are projecting a Summer 04 completion date for the MRE. CRI-
The current projected completion date is August 2, 2004 for the first,
second, third and seventh floors. There is a pending NIH grant that
will provide funding to finish floors 5&6. (The highest score
in the country was given to our researchers on this NIH grant. Design changes
have slowed construction in several areas: The second floor breakthrough was redesigned to provide fire separation between the new and existing buildings. Another revision was needed to provide access from the CRI to the freight elevators and to add a door to a faculty office from the main hallway rather than through an existing office. The BSB lobby
and stairs to the second floor lobby have been the greatest challenge
to the designers, the construction team and us, the owners. It was
discovered that the original design of the structural steel for the
staircase ran through an existing bus duct-- both normal and emergency
power for BSB run across the lobby, and to move the bus Construction site is off limits-- Please be reminded that the construction site is off limits to all pedestrian traffic. Please pass this along to all new students and employees. Also, as the building takes shape and curiosity and excitement mount, it is important to remember that visitors to the new building must wear hard hats and must be accompanied by the project manager. To schedule a tour please call Mac McClinton at 792-4589. Thanks! Attendees- Mac McClinton, Leslie Kendall, Laura Walters, Dr. Charles Darby, Dr. Tom Trusk, Dr. Jim Goodrich and Dwayne McMillan |
||||||
|
Content last updated: Thursday, 7 August, 2003 |
||||||